07 / 23 / 2026

Thursday Stand Up

Sprint 2026-13 · Jul 13–24
Gen-1 MVP integrated prototype

Announcements

Safra is on PTO for ~2 weeks starting today — async only (~12 hrs ahead). TQ is running stand-ups; Wale covers Friday. Route all manufacturing comms to manufacturing@mesaquantum.com (TQ + Wale monitoring).

Updates we need today

The Sprint 2026-13 items flagged off-track — i.e. what we're actively pursuing.

  • Boards & blades out for fab/quote at IEC (Innovate)? Cards → Nick · PD + vapor-cell blades → Curtis · assembly → Brian. Compute-card PO is the long pole. Target: parts in-hand Aug 10.
  • NPL review slides — Wale needs team inputs. Who still owes a slide, and what's the deadline?
  • Robbie knowledge transferCritical · due today
    Reassign Robbie's items (System Level Test, ADEV, startup validation) to Newton & Gabby with him shadowing. Influx → Beryllium cutover while he's here.

Two brief updates

  • Oscilloquartz: open to initial-unit delivery the week of Aug 24 (confirm: delivery vs. on-site test). OK with pinch-off packaging for 2026 units — but the copper tube must move to ≥15 mm from the base, opposite side from current.
  • A clock for Jon with an STM adapter — unblocks firmware / heater debug (heater fault currently suspected in firmware).